Chairman Michael Gray called the meeting to order at 6:00 PM in the Terminal Building Conference Room at the Morehead-Rowan County Regional Airport. Other members present were Tom Fossett, Don Laferty, Charles Derrickson, Porter Dailey, Stanley Click, Tim James, Ron Oliver, and Eric Stinson. James LeMaster was absent. Guests present were Tracey and Mike Potter – Fixed Base Operator; Magistrate Harry Clark – Rowan County Fiscal Court liaison; Ben Brandstetter – Brandstetter Carroll Inc.; Earl Rogers – Attorney; and Barbara Marsh – Assistant Secretary-Treasurer.
The Minutes of the December 27, 2012 meeting were presented. The motion to approve the December Minutes was made by Mr. Oliver, and seconded by Mr. Laferty, and unanimously approved.
Mr. Laferty presented the results of the Audit Committee which met at 5:00 PM. He introduced Mr. Joel Lane – Auditor, John T. Lane and Associates, LLC, Certified Public Accountants. Mr. Lane reviewed the Audit Report for Fiscal Year 2012 (July 2011-June 2012). His findings included an unqualified clean opinion and no findings. The motion to accept the FY12 Audit Report was made by Mr. Oliver, seconded by Mr. James, and unanimously approved.
Mr. Dailey presented the Financial Report for the period ending December 31, 2012. The largest expense was the purchase of the fuel truck – $4,000. The motion to accept the December 2012 Financial Report was made by Mr. Stinson, seconded by Mr. Click, and unanimously approved.
Mr. Dailey reported that the Certificate of Deposit held by the Whitaker Bank has a balance of $38,286.11. Our Fixed Base Operators’ two-year contract is a remaining obligation of $35,000. In order to insure the availability of funds for the contract, a restriction on the Certificate of Deposit held at Whitaker Bank is in order. The motion to restrict $35,000 of the Certificate of Deposit to the FBO contract was made by Mr. Oliver, seconded Mr. Dailey, and approved unanimously.
REPORTS
Tracey Potter gave a report on the status of the FBO and Airport activities. She advised the status of fuel sales, grounds maintenance, and hanger activities.
Ms. Potter reported that fuel sales for the month of December were 833 gallons of 100LL and 1,244 gallons of JETA fuel with 940 gallons of that pumped out of the fuel truck. Several sales would not have occurred if the fuel truck had not been available. Another 6,000 gallons of JETA fuel was ordered. The balance of remaining fuel is approximately 8,100 gallons of 100LL and 6,000 gallons of JETA fuel.
Ms. Potter reported that the monthly community hangar report includes PHI Helicopter – $300; Josh Smith – $150, and Kevin Mays – $150, for a total of $600.
Mr. Potter reported that ramp tie downs for Justin Potts and Robert Thomas for the period October-December and January-March was received. The amount is $75 per quarter for a total of $300. Leases for the tie downs for Mr. Potts and Mr. Thomas are being collected.
Ms. Potter reported that a brake line failed on the Courtesy Car. Major Brands Inc. made the repairs
Ms. Potter reported on the following: the December 29 bus trip to the Dayton Air Force Museum was a success with 32 attending; another Pancake and Sausage Breakfast on February 2; the strobe light on runway 20 was in need of repair; the ramp area had been swept; coat hooks were installed on each restroom door in the Terminal Building and all walls in the Terminal Building had been washed.
Ms. Potter reported that an accident occurred at the Airport. David LeGuire was working by himself on a rainy Sunday afternoon and fell down while unloading equipment. The information which came over the emergency networks was that an airplane had run over a person which was untrue.
Mr. Brandstetter reported on six projects.
- AWOS Project. AWI (AWOS Supplier) will be on-site in February to complete the AWOS system installation. Data will be gathered and will be available for access. AWI is providing FAA with data for the licensing process. When the license is back from the FAA, the AWOS will be operational; however, data will be available in the interim after hook up.
- T-Hangar Construction. Per discussion with FAA on 1/30/13, the FY 2013 AIP funds are not 100% authorized at this time. Full funding is dependent upon Congressional action. After discussing three options for going forward, option 2 was accepted to advertise the project for bid in February. A short-term bank note to cover the gap until FY 2014 dollars are available may be needed. The Board’s percentage local match is 2.5% of the project cost.
- DBE Plan. DBE Plan was approved by the FAA on 11/14/12. Information about this project will be available in the Terminal Building as a bulletin board item or on the counter.
- Runway Storm Improvements. On hold until spring.
- KTC Funded Paving Improvements. Submitted in 2012 but not funded. Mr. Brandstetter will inquire when the next round of funds will be approved.
- Temporary Runway Repair for Runway 2. The Walker Company completed this work during the week of December 3rd, per schedule. It will be funded at 100% by a state grant.
Mr. James and Dr. Derrickson, Buildings & Grounds Co-Chairs, reported that a Buildings and Grounds Handbook had been developed. It is a guideline for ground and facility planning and execution and included such items as maintenance of equipment, fertilizer needs, grounds operation, erosion control, mowing frequency, development of grasslands and hay, fertilization and costs. Priority items include liming/fertilizer/seeding and erosion control. Purchases need to be in large quantities for price control. The applications need to begin in March. Mr. James and Dr. Derrickson asked that a budget be developed for their application. Mr. Gray will resubmit a state request for reimbursement of matting from a prior year. A motion to approve the Buildings and Grounds Handbook was made by Mr. Dailey, seconded by Mr. Click, and approved unanimously.
NEW BUSINESS
Mr. Laferty reported that options for a 3-letter identifier required by the FAA for a TAF and thus eligibility for an advanced weather station had been narrowed to three possibilities and he was recommending SYM as the new airport identifier (to replace M92). Mr. Dailey seconded the motion and it was unanimously approved.
Mr. Dailey reported on the Financial Manual which was developed in response to an FAA requirement regarding grant risk management. The Financial Manual contains the processes in place to handle all funds, procurement, management of files, and security of data. The Executive Committee had approved the Manual to meet an FAA submittal deadline. The motion to approve the Financial Manual was made by Mr. Stinson, seconded by Mr. James, and approved unanimously.
Mr. Brandstetter reported on a Permanent Runway Fix for runway 2. A permanent fix is being reviewed at this time, but will likely be deferred until 2014. There is a need to localize the problem, but there are no signs of weakness at this time. The State will not fund the permanent repair.
Mr. Stinson reported on next year’s planned Community Day and Air Show – September 21, 2013. The event needs to have sponsorship funds to cover all expenses for the event or the event will not be held. Last year’s event was subsidized by $3,500. Suggestions included a gate charge (by the carload). Funds for insurance and performer fees will be allocated first. Funds for the event need to be committed by April 1. Mr. Stinson and Dr. Fossett, Committee Co-Chairs will develop a budget for the Community Day and Air Show.
OTHER BUSINESS
Mr. Oliver expressed appreciation for the flower arrangement which was sent during the passing of his Mother.
ADJOURNMENT
Mr. Gray adjourned the meeting 7:30 PM.